AI News Page

← 2026-11-19 edition

THE SHORT VERSION

GOOGLE SIGNED FOR 50 MEGAWATTS OF VOLCANO POWER — FIRST WATTS IN 2030

Google signed a power purchase agreement to buy 50 megawatts of superhot geothermal power from Quaise Energy's Project Obsidian in Central Oregon, the companies announced November 17 — the world's first commercial-scale superhot rock geothermal deal. The power, enough for about 50,000 households, is slated to support Google's data centers in The Dalles starting as early as 2030, once the plant is built.

The catch is in the calendar: the first well is still being drilled, aiming nearly three miles down to rock at about 700°F, and the plant itself would cost about $350 million to build. Quaise confirmed to Canary Media the agreement is valued at more than $500 million — a contract to buy future electricity, not an upfront investment. The first phase uses conventional drilling; a planned second phase would be the first in the world to use Quaise's millimeter-wave drill, reaching rock up to 850°F for a planned 250 megawatts total.